Location

17 - 25 Hampstead Road, Maidstone, Victoria    map

Last updated: July 2010

We are pleased to provide you with the latest Construction Update from the developer, JMC.
 
We note Stage 1 completion is expected to be Late September this year, Stage 2 Late 2010/early 2011, and Stage 3 now expected to be June 2011.
 
Precinct 7 Stage 1
  • Majority of internal fit out including tiling, joinery and plastering complete
  • Majority of external facades and finishes complete

Precinct 7 Stage 2

  • Structure complete
  • Works on internal services have commenced
  • Works on external finishes have commenced

Precinct 7 Stage 3

  • Earth works are underway and nearing completion
  • Foundations are underway