Location
1037 - 1041 Dandenong Road, East Malvern, Victoria
We are pleased to provide you with the latest update and photograhs of your property in Seed from the Goal Property Group.
Generally, the following works have been completed:
- Site set-up
- Demolition
- Reinforced concrete slabs to Units 5-17
- In-slab services
- Excavation to the basement
- Shotcrete wall to basement
- Basement ground slab to Units 1-4
- Steel Columns
- Upper floors
- Roof to Units 5-6, 7-11 & 14-17
- Timber stud wall framing to Units 5-6, 7-11 & 14-17
- Windows to Units 5-6, 7-11 & 14-17
- Lighting to basement carpark
Generally, the following works are in progress:
- External brickwork walls to Units 5-6, 7-11 & 14-17
- External QT & foam cladding to Units 7-11 & 14-17
- Timber stud wall framing to Units 1-4
- Plasterboard lining and insulation to 5-6, 7-11 & 14-17
- Plumbing rough-in to Units 5-6, 7-11 & 14-17
- Electrical rough-in to Units 5-6, 7-11 & 14-17
- Mechanical services to Units 5-6, 7-11 & 14-17
The works are running on schedule and we anticipate completion around middle of August 2012.