103 Atherton Road, Oakleigh, Victoria    map

Last updated: August 2010

We are pleased to provide you with new photographs which demonstrate work is progressing well at The Oak Apartments with completion still anticiapted in August.
 
As you can see we are nearing completion. The occupancy permit has been issued and the titles are approximately three weeks away.
 
We expect settlement to take place in approximately five weeks.
 
 
Generally, the following works have been completed:
Apartment Building Heritage Building Townhouses
Excavation Demolition works Ground slab
Underpinning and footings Brickwork make-good Columns
Precast concrete wall panels Insulation Upper floors
Precast concrete columns Plasterboard lining  Windows
Suspended upper floor slabs Tiling External wall cladding
Roof framing and sheeting Internal doors

 Roof framing and sheeting

Windows Sanitary fixtures  Timber stud walls
Timber stud wall framing Kitchen joinery  External walls
Balustrades  Electrical fit-off  Plasterboard lining
External walls  Mechanical rough-in  Plumbing rough-in
Tiling  Electrical rough-in  Electrical rough-in
Sanitary fixtures  Plumbing rough-in  
Kitchen joinery    
Plasterboard lining    
Plumbing & Electrical rough-in    
Car-stacker concrete pits    
Electrical fit-off    
Lift    
A/C fit-off    
External Works  
Site preparation
Concrete driveway
Stormwater, sewer and fire services 

 Generally, the following works were in progress :
Apartment Building Heritage Building Townhouses
Kitchen splashbacks Painting Joinery
Appliances Appliances Painting
Carpet A/C fit-off Electrical fit-off
External wall rendering Shower screens Sanitary fixtures
Minor painting   Hot water units
External Works
Stormwater pits
Electrical services