We are pleased to provide you with the latest update and photographs of your property in Riviere (Hank Dye and Boiler House). As you can see there has been lots of activity on site.

At this stage, we are still anticipating completion in Early 2014.

We will keep you informed as the building progresses.

If you have any queries please do not hesitate to contact your Senior Property Adviser.

 

CONSTRUCTION REPORT

Concrete structure works are progressing on site.

Boiler House levels B2, B1, 1 and 2 structures are completed. Level 3 suspended slab is completed and precast panels are being installed. Level 4 formwork is underway and concrete to form the Level 4 slab will be poured soon. Services to the basement are being roughed-in.

Hank Dye levels B2, B1 and 1 structures have been completed. Level 2 slab has been poured and the precast panels to that level are being installed. Level 3 formwork is nearing completion and concrete reinforcement installation has commenced.

Cascade and Yarra (part) B1 slab is being poured and some precast panels are being installed. Bulk excavation and foundation piling continues at the Trenerry Crescent end of the site.